A revived Inga III, an overhaul of DRC’s state-owned power utility, SNEL, and a growing list of public-private partnerships have put the Congolese power sector back on the front foot after years of strain. But the obstacles remain daunting.
The Inga I and II dams on the Congo river in the DRC have been in service since 1971 and 1982. © AFP
Share
The Democratic Republic of Congo, a mining giant plagued by chronic power cuts, wants to speed up its efforts to bring electricity to its people, and a number of recent initiatives and breakthroughs point that way.
The vast Inga III dam project, which promises 11,000 megawatts (MW) of power for the country, is coming back to life after years of deadlock. In late October, the DRC and the US held the first meeting of their coordination and governance committee at the World Bank’s Paris offices. A working group will meet monthly from November 2026 to April 2027 to carry out the technical and financial groundwork for Inga III.